The final service on Sir Gareth will be completed today. A restoration crew will begin on Monday to complete cleanup and temporary asphalt repairs by the end of next week.
The main sewer crew is finishing the large maintenance hole at Sir Lancelot and Sir Pellias. Early next week, they will move to Sir Kay to complete the remaining section of sewer upgrades between Sir Lancelot and Sir Gareth. This work is expected to take about two weeks.
Two services on Sir Lancelot will need realignment following the storm sewer upgrade. This work will begin next week.
Once Sir Gareth is complete, the restoration crew will move to Sir Lancelot to do final cleanup and temporary restoration between Sir Kay and Sir Pellias.
Everything remains on track to be completed before the holiday season, with the contractor demobilizing until April.
Church St - Notice sent October 2025 CLICK HERE
Additional notices will be provided when curb replacements begin, expected within the next 7-10 days (weather permitting) Current schedule:
- Water service works will begin with two crews, expected to be complete within two weeks
- The sub-drain installation under curbs to be completed by Friday.
- Curb replacements to start within two weeks
- Granular materials for full road reconstruction are already in place.
- Base asphalt is planned for completion by the end of the third week of December, following curb installation.
Safety reminder
There was an attempted equipment theft last night, spotted by a resident at 1am. Contractors will not be working unusual hours. If you notice anything out of the ordinary, please contact York Regional Police.